Skip to main content

click here for schoolTool click here for Menus click here for Facebook click here for Twitter click here for the events calendar click here to report bullying   

Capital Project Update

Completed Project(s)
Over this past summer, the middle school added an additional row of parking spaces, interior wallpaper was removed and walls painted, and a basketball court near the playground.


Upcoming Project(s)
Very soon the middle school basketball court will have a top coat and stripes, the playground will have a new look with additional equipment, and new bleachers in the large gym.



2018-2021 Capital Project Timeline (Tentative Dates*)

Phase 1 Schedule
  • Construction Documents – Dec. 2017 through July 2018 (8 months)
  • SED Submission – July 2018
  • Constructability Review/Estimate – Fall 2018
  • SED Approval – March 2019 (8 months)*
  • Bidding – April 2019*
  • Contractor Mobilization/Submittals – May 2019*
  • Construction – Summer 2019 into the 2019-2020 School Year*
  • Closeout – Summer 2020*

Phase 2 Schedule
  • Construction Documents – Aug. 2018 to April 2019 (9 months)
  • SED Submission – April 2019
  • Constructability Review/Est. – Summer 2019
  • SED Approval – Dec. 2019 (8 months)*
  • Bidding – Jan. 2020*
  • Contractor Mobilization/Submittals – Feb. 2020*
  • Construction – Spring, summer, and fall of 2020*
  • Closeout – Spring 2021*

DISTRICT INFO


QUICKLINKS


SCHOOLS


Solvay Union Free School District
Jay Tinklepaugh, Superintendent
PO Box 980
299 Bury Drive
Syracuse, New York 13209
Phone: (315) 468-1111


www.solvayschools.org

solvay footer logo
Developed by CNYRIC