Skip to main content

click here for schoolTool click here for Menus click here for Facebook click here for Twitter click here for the events calendar click here to report bullying   

Capital Projects

Updates......

The new transportation facility is taking shape.  Thank you to the residents near the existing structure for your patience and understanding of the noisy work that will be ongoing while the new center is being built with an approximate completion in 18 months.
 


A few summer projects are happening at Solvay Middle School.  The building is receiving a new roof and a new set of stairs.  The main entrance/office are being renovated to provide additional security for our students and staff.







2018-2021 Capital Project Timeline (Tentative Dates*)
Phase 1 Schedule
  • SED Approval – March 2019 - Complete
  • Bidding – April 2019 - Complete
  • Contractor Mobilization/Submittals – May 2019 - Complete
  • Construction – Summer 2019 into the 2019-2020 School Year - In Progress
  • Closeout – Summer 2020*
Phase 2 Schedule
  • Construction Documents – Aug. 2018 to April 2019 - Complete
  • SED Submission – April 2019 - Complete
  • Constructability Review/Est. – Summer 2019 - In Progress
  • SED Approval – Dec. 2019 (8 months)*
  • Bidding – Jan. 2020*
  • Contractor Mobilization/Submittals – Feb. 2020*
  • Construction – Spring, summer, and fall of 2020*
  • Closeout – Spring 2021*

DISTRICT INFO


QUICKLINKS


SCHOOLS


Solvay Union Free School District
Jay Tinklepaugh, Superintendent
PO Box 980
299 Bury Drive
Syracuse, New York 13209
Phone: (315) 468-1111


www.solvayschools.org

solvay footer logo
Developed by CNYRIC