Skip to main content
 
 

Capital Projects

Updates......

Solvay High School
  • The auditorium renovations are in the final stages.
Solvay Elementary School
  • Air conditioning, new single point of entry, and additional parking is complete.  Some work continues throughout the building.
2018-2021 Capital Project Timeline (Tentative Dates*)

Phase 2 Schedule

  • Construction Documents – Aug. 2018 to April 2019 - Complete
  • SED Submission – April 2019 - Complete
  • Constructability Review/Est. – Summer 2019 - Complete
  • SED Approval – Dec. 2019 (8 months)* - Complete
  • Bidding – Jan. 2020* - Complete
  • Contractor Mobilization/Submittals – Feb. 2020* - In Progress
  • Construction – Spring, summer, and fall of 2020*- In Progress
  • Closeout – Spring 2021*
Jay Tinklepaugh, Superintendent
PO Box 980, 299 Bury Drive
Syracuse, New York 13209
Phone: (315) 468-1111