Skip to main content

click here for schoolTool click here for Menus click here for Facebook click here for Twitter click here for the events calendar click here to report bullying   

Capital Projects

Updates......

Solvay Middle School
Just before the weather changed, the playground was complete.  During December's holiday recess, the floor was refinished in the small gym and new bleachers were installed in the large gym. 

Transportation
Transportation is moving to their temporary location.  The move will be complete by February 25.  The demolition of the existing building will begin in early March, pending weather.  A letter to residents near the existing structure is being mailed; also below.  The new center is scheduled to be complete in approximately 18 months.

 


 
 





 
 
 









2018-2021 Capital Project Timeline (Tentative Dates*)
Phase 1 Schedule
  • Construction Documents – Dec. 2017 through July 2018 (8 months)
  • SED Submission – July 2018
  • Constructability Review/Estimate – Fall 2018
  • SED Approval – March 2019 (8 months)*
  • Bidding – April 2019*
  • Contractor Mobilization/Submittals – May 2019*
  • Construction – Summer 2019 into the 2019-2020 School Year*
  • Closeout – Summer 2020*

Phase 2 Schedule
  • Construction Documents – Aug. 2018 to April 2019 (9 months)
  • SED Submission – April 2019
  • Constructability Review/Est. – Summer 2019
  • SED Approval – Dec. 2019 (8 months)*
  • Bidding – Jan. 2020*
  • Contractor Mobilization/Submittals – Feb. 2020*
  • Construction – Spring, summer, and fall of 2020*
  • Closeout – Spring 2021*

DISTRICT INFO


QUICKLINKS


SCHOOLS


Solvay Union Free School District
Jay Tinklepaugh, Superintendent
PO Box 980
299 Bury Drive
Syracuse, New York 13209
Phone: (315) 468-1111


www.solvayschools.org

solvay footer logo
Developed by CNYRIC