Capital Projects
Updates......
Solvay High School- The auditorium renovations are in the final stages.
- Air conditioning, new single point of entry, and additional parking is complete. Some work continues throughout the building.
2018-2021 Capital Project Timeline (Tentative Dates*)
Phase 2 Schedule
- Construction Documents – Aug. 2018 to April 2019 - Complete
- SED Submission – April 2019 - Complete
- Constructability Review/Est. – Summer 2019 - Complete
- SED Approval – Dec. 2019 (8 months)* - Complete
- Bidding – Jan. 2020* - Complete
- Contractor Mobilization/Submittals – Feb. 2020* - In Progress
- Construction – Spring, summer, and fall of 2020*- In Progress
- Closeout – Spring 2021*